Bengaluru Metro's Pink Line: Tunnelling Work On City's Longest Underground Corridor To Be Completed By 31 August, Launch In 2025
V Bhagya Subhashini
Apr 16, 2024, 04:57 PM | Updated 05:03 PM IST
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Bengaluru's metro network is on the brink of a major milestone with the nearing completion of the Pink Line's extensive underground tunnel. Connecting Bannerghatta Road to Nagawara, this 13-kilometre tunnel is in its final stages of construction and is set to be finished by August this year.
The Pink Line covers 21.26 kilometres, featuring a 13.76-kilometre underground section and a 7.5-kilometre elevated portion, with 18 stations, including 12 underground.
The Bengaluru Metro Rail Corporation Limited (BMRCL) has divided the tunnelling project into three phases. The first two phases have been successfully wrapped up, with the third phase currently at 94 per cent completion rate.
A BMRCL official stated, “The third phase involves excavating 935 metres of tunnel between KG Halli and Nagawara, using advanced Tunnel Boring Machines named Tunga and Bhadra. Tunga and Bhadra, which began their operations in February and April respectively, are progressing well towards completing their respective sections by 31 July and 31August," reports Economic Times.
The completion of these tunnelling phases will set the stage for subsequent track laying, civil works, and the installation of vital infrastructure for the Pink Line.
BMRCL aims to finalise all civil and track-laying work on the Pink Line by the second half of 2024, paving the way for traction, signalling, and system installations.
Once the Pink Line becomes operational, it promises to alleviate transportation challenges and improve connectivity for Bengaluru's residents and commuters.
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.