Trail Run Of Mumbai Metro Line-3 Scheduled On 75th Independence Day: Report
V Bhagya Subhashini
Aug 13, 2022, 05:15 PM | Updated 05:15 PM IST
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
The prototype train for the Metro Line 3 (Colaba-Bandra-Seepz) underground corridor is expected to run trials on August 15, 2022.
The three kilometres stretch between Sariput Nagar and Marol Naka metro station would be used for the testing.
The Mumbai Metro Rail Corporation (MMRC) has purchased a battery-operated shunter for the Metro car depot. For the Colaba-Bandra-Seepz Metro Line-3's first eight-car prototype train, this battery-operated rail-cum-road shunter was successful.
"We have procured a battery-operated shunterfor Metro car depot. This battery-operated rail-cum-road shunter has successfully formed the first 8-car prototype train for the Colaba-Bandra-Seepz metro line-3," a Mumbai Metro Rail Corporation (MMRC) representative stated, reports The Economic Times.
The shunter is produced under the Make-In-India strategy, thanks to a joint venture and technology transfer agreement with the NITEQ of the Netherlands.
The Alstom trains produced cars for a prototype train whose manufacturing plant is based in Sri City, Andhra Pradesh.
By 2023, MMRCL hopes to have finished building Metro Line 3. These trains will run on a 25 KV AC traction supply and have a maximum passenger carrying capacity of 2,350 passengers.
Mumbai Metro Line 3
Metro Line 3 is a 33.5 km long underground corridor running along Colaba-Bandra-SEEPZ. The corridor length is marked with 27 key stations, out of which 26 will be underground.
Metro Line 3 would connect Mumbai’s key financial hubs, such as Nariman Point, Bandra-Kurla-Complex, Fort, Worli, Lower Parel, Goregaon, etc. The metro will provide for the first time connectivity to the airport, Nariman Point, Cuffe Parade, Kalbadevi, Worli, BKC, Airport, SEEPZ and MIDC.
Besides, two crucial heritage stations of Mumbai, i.e. CSTM and Churchgate, will also get joined through the alignment.
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Introducing ElectionsHQ + 50 Ground Reports Project
The 2024 elections might seem easy to guess, but there are some important questions that shouldn't be missed.
Do freebies still sway voters? Do people prioritise infrastructure when voting? How will Punjab vote?
The answers to these questions provide great insights into where we, as a country, are headed in the years to come.
Swarajya is starting a project with an aim to do 50 solid ground stories and a smart commentary service on WhatsApp, a one-of-a-kind. We'd love your support during this election season.
Click below to contribute.