Bengaluru Metro: Construction Of Bettahalasur Metro Station On Airport Line To Begin Soon On PPP model
V Bhagya Subhashini
Jul 04, 2023, 10:27 AM | Updated 10:27 AM IST
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
After three years of indecisiveness, the issue of accommodating the Bettahalasur Metro station on the KR Puram-Kempegowda International Airport (KIA) line has finally been resolved.
DC Nataraj, the chief engineer of Bengaluru Metro Rail Corporation BMRCL, has confirmed that the station, situated one km from the IAF campus, will be built on the Public-Private Partnership (PPP) model as originally planned. Embassy Group will provide the funding, while BMRCL will handle the construction work.
According to a senior Metro official, a formal Memorandum of Understanding (MoU) between BMRCL and the Embassy Group will be signed soon. The Embassy Group has already made a token contribution of Rs one crore for the station.
The station will be located between Bagalur Cross and Doddajala stations, with an estimated cost of around Rs 140 crore.
In April 2020, the Embassy Group initially agreed to fund the station for easy access to its residents in the Embassy Boulevard complex. However, due to internal financial issues, they later withdrew their funding. As a result, BMRCL announced in December 2022 that they would not proceed with the station.
Additionally, the Jakkur Plantation station, which was also uncertain, will be included on the airport line. The Jakkur Plantation station will be located between the GFTS Campus and Kogilu Cross. With a budget of Rs 120 crore, itwill be jointly constructed by Bagmane and Century Group on the Airport Line.
In response to public demand, the State Government's High Powered Committee has approved the addition of the Chikkajala station to the metro line. It will be situated between Bettahalsuru and Doddajala stations.
The Chikkajala station, which was added to the line based on public demand, has been approved by the State Government's High Powered Committee.
The 36.44-km Airport Line is divided into three packages: K R Puram to Hebbal (Pkg 1), Hebbal to IAF Campus (Package 2), and IAF to KIA (Package 3).
The completion deadline for the entire line is set for June 2026.
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.