Infrastructure

Agra Metro: First Tunnel Breakthrough Achieved In Record Time Of 77 Days

Amit MishraApr 26, 2023, 10:04 AM | Updated 10:22 AM IST
Tunnel Breakthrough, Agra Metro

Tunnel Breakthrough, Agra Metro


In a major milestone for Agra Metro Rail Project, TBM 'Yamuna' achieved first breakthrough at Agra Fort Metro Station on Tuesday (25 April).


Tunnel construction workers.

Sushil Kumar, managing director, Uttar Pradesh Metro Rail Corporation (UPMRC) said, “This is the fastest breakthrough (distance travelled by TBM for making tunnel between two stations) achieved by any metro project in the country, in a record 77 days since TBM launch”.

Earlier in February 2023, Uttar Pradesh CM Yogi Adityanath had commissioned two TBMs — Yamuna and Ganga — to build 3 km long tunnel of the 6 km priority corridor between Taj East Gate and Jama Masjid.

The TBM Yamuna, after its first breakthrough at Agra Fort Metro Station, will go on to construct tunnel till Taj Mahal Metro Station.


“The two TBMs are operational. A safe distance between the two TBMs has been maintained as part of safety procedure,” said UPMRC official.

Two Routes

The 29.4 km Agra Metro has two corridors with 27 stations.

Agra Metro Map

The 14 km first corridor between Taj East Gate and Sikandra is now under development and has 13 stations — six elevated and seven underground.

The second corridor to be built between Agra Cantt and Kalindi Vihar in Agra City will be 15.4-km-long and will be completely elevated with 14 stations.

Priority Corridor


It has three elevated metro stations - Taj East Gate, Basai and Fatehabad Road along with three underground metro stations — Taj Mahal, Agra Fort and Jama Masjid.

The civil work-related to the elevated stretch was completed when the last U-Girder was erected on 13 March.

Similarly, the UPMRC has already constructed all the three elevated stations of Taj East Gate, Basai and Fatehabad Road.

Taj East Gate Metro Station

Basai metro Station

Fatehabad Road Metro Station

However, the tunneling work on the priority corridors' 3 km underground section between Taj Mahal and Jama Masjid started only in February 2023.

With the breakthrough of the TBM at Agra Fort station, the commissioning of the Priority Corridor is expected to meet August 2024 deadline.


Prime Minister Narendra Modi had laid the foundation stone of Agra Metro Project in December 2020.

Join our WhatsApp channel - no spam, only sharp analysis