Infrastructure

Namma Metro: Entire 21.25 Km Stretch Of Gottigere-Nagawara Pink Line To Open In March 2025, BMRCL Reports 72% Tunnelling Work Completion

India InfrahubFeb 16, 2023, 11:08 AM | Updated 11:11 AM IST
TBM Lavi (Credit: The Metro Rail Guy)

TBM Lavi (Credit: The Metro Rail Guy)


With over 72% of tunnel work completed, the Bangalore Metro Rail Corporation Ltd. (BMRCL) has announced that the 21.25 km Pink line of Namma Metro will be commissioned by March 2025.


The Pink line Of Phase 2 of Namma Metro will connect Kalena Agrahara station (previously called Gottigere) on Bannerghatta road in the southern city of the city with Nagawara on Outer Ring Road on the north side. The Pink Line is predominantly an underground network (14 km) with 7 km of elevated line.


Tunnelling Work Progress


TBM Status/ Mahesh Nanjunda Via Skyscraper City Forum

TBM Lavi on Wednesday achieved a breakthrough by completing its drive at Rashtriya Military School station (Vellara Junction). Five of the nine TBMs - Urja, Varada, Avni and now Lavi- have completed the boring operations.

"TBM Lavi, which started its tunnelling at Shivajinagar on March 26, 2021 achieved a breakthrough at MG Road station after completing 1074m of tunnelling on April 15, 2022. It further started tunnelling from MG Road on May 26, 2022 and completed the drive on Wednesday up to RMS (Vellara) station covering a tunnel length of 1134m," the official press release from BMRCL said.

The press release added that TBM Vindhya, which is cutting through from Pottery Town station to Shaadi Mahal shaft, is expected to complete the drive by the end of this month.

"This underground section (of the Pink Line) has been divided into four contract packages and nine TBMs have been deployed for completing this tunnelling work. Out of this, three TBMs: Urja, Varada & Avni have already completed their designated length of tunnelling. Lavi is the fourth TBM to complete its drive," it said.


Afcons Infrastructure is executing the other package - a 3.65 km underground portion from Dairy Circle Ramp to Rashtriya Military School.

In October last year, Rudra, one of the TBMs deployed by Afcons, was stuck for a reason after encountering a massive pile of garbage (plastic buckets, tyres, bags, disintegrating bones etc.) underground at a depth of 33 feet from the surface. Local authorities attributed it as a quarry land that was converted into a dumping site. The dumping site was later filled with debris and sand before turning into a housing area.

Join our WhatsApp channel - no spam, only sharp analysis