Union Railways Minister Ashwini Vaishnaw on Monday (6 June) said that the government is targeting to run India's first bullet train between Gujarat's Surat and Bilimora by 2026 as there is good progress in this direction.
“There has been good progress in the construction of infrastructure for the bullet train between Ahmedabad and Mumbai, and the work is being done at a high speed,” Vaishnaw was quoted in a Free Press Journal report as saying.
The Railways Minister said this after inspecting the progress of the Mumbai-Ahmedabad bullet train project in Surat.
"We are keeping the target of running the first bullet train between Surat and Bilimora in 2026. The progress is very good, and we are confident of running the train by that time,” he told reporters, reports The Tribune.
Bilimora is a town in south Gujarat's Navsari district, and is one of the 12 stations on the Mumbai-Ahmedabad bullet train route.
The minister informed that the pillars for the bullet train track have been casted on a length of 61 km and the work is simultaneously going on at around 150 km length of the route.
He said that the work on the Surat bullet train station is likely to be completed by 2024.
Apart from Surat, work on three more stations – Vapi, Bilimora and Bharuch – is in full swing and also likely to complete by 2024.
He said every month around 300 pillars are being erected, covering a distance of around 12 km.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.
Latest