News Brief
NCRTC constructs spans in a section of the Delhi-Ghaziabad-Meerut RRTS corridor.
In a major boost to regional connectivity in NCR, the government has allocated Rs 4,710 crore to country’s first Regional Rapid Transit System (RRTS) project in the Union Budget.
Construction work on the entire 82 km long Delhi-Ghaziabad-Meerut RRTS corridor is in full swing. The corridor will have 25 stations, including two depots and one stabling yard.
So far, 16 km viaduct of priority section, 1200 piers, and 9,900 piles have been concreted. Foundation work has been completed for 56 km of the corridor.
The 17 km priority section between Sahibabad to Duhai is scheduled to be operational by March 2023 and trial runs are expected to begin this year. The complete corridor will be opened to the public by 2025.
"RRTS is a strategic investment of the government to transform the mobility in NCR in line with the Gati Shakti masterplan. The continued allocation to RRTS reinforces government’s focus on infrastructure expenditure to catalyse the economic revival after the impact of pandemic," said NCRTC MD Vinay Kumar Singh.
"Despite the impact of pandemic on the pace of work and capital expenditure, we are committed to work with our construction partners and other stakeholders to uphold the responsibility bestowed upon us by the government in keeping the implementation of RRTS as per schedule," he added.
NCRTC is a joint venture of the Government of India (50 per cent) and State Governments of Haryana (12.5 per cent), NCT Delhi (12.5 per cent), Uttar Pradesh (12.5 per cent) and Rajasthan (12.5 per cent).
It is mandated to design, construct, finance, operate and maintain RRTS in NCR and works under the administrative control of the Ministry of Housing and Urban Affairs.