On 24 November, Prime Minister Narendra Modi said the Mopa airport in Goa built at a cost of Rs 3000 crore, will be commissioned soon.
He was virtually addressing youth who were given appointments in Goa government departments during the Rojgaar Melava organised by the Goa state government.
"Thousands of Goans have received employment during the construction of this airport,” he said.
While the original estimate for constructing the airport was Rs 1,900 crore, it was later revised to Rs 2,615 crore due to the cost escalation and time overrun caused by environment-related litigations. The Covid-19 pandemic also disrupted the project completion schedule.
In its first phase, the airport is expected to cater to 4.5 million passengers; at the end of the fourth phase, its passenger handling capacity is expected to be 13 million.
The Goa international airport at Dabolim in South Goa will continue to remain operational even after the commissioning of the Mopa international greenfield airport in North Goa, Chief Minister Pramod Sawant said in July.
The union government has spent over Rs 850 crore on the expansion and upgradation work of the Dabolim airport in the past four to five years.
Due to this, at present, only 70 flights land on a daily basis at the Dabolim airport. No landing is permitted from 9 a.m. to 2 p.m. at the facility. After the commissioning of the Mopa airport, the number of flights landing in Goa will go up to 150, Chief Minister Pramod Sawant had said in July this year.
On 5 September, the first commercial aircraft successfully landed and took off from Goa's future international airport at Mopa. It was part of the airport's Required Navigation Performance (RNP).