News Headlines

Tracking National Highway Work: Average Per Day Road Construction Jumps To 22.23 Km, 8,400 Km Awarded And 6,800 Km Constructed

Amit MishraFeb 15, 2023, 04:32 PM | Updated 05:41 PM IST
Mumbai-Agra National Highway near Kasara Ghat in Maharashtra

Mumbai-Agra National Highway near Kasara Ghat in Maharashtra


The Ministry of Road Transport and Highways (MoRTH) has constructed 6,803 km of National Highway (NHs) between 1 April and 31 January in FY 2022-23 as compared to 6,684 km constructed during the same period in FY 2021-22.

On a kilometer basis, this translates to 22.23 km per day on an average, slightly up from 21.84 km constructed per day in 2021-22 for the same period, shows official data.

Apart from laying more highways, the Ministry has also stepped up on awarding work.  

A total of 8,400 km of highways have been awarded up to January in 2022-23 financial year, a jump of 22 per cent over 6,883 km awarded during the same period in the last financial year.


Consistent Improvement

The pace of National Highways construction has increased consistently between 2014-15 and 2021-22 due to the systematic push through corridor-based National Highway development approach.

In the financial year 2020-21 which saw the Covid-induced lockdown, the Ministry constructed a record 13,327 km of national highways. In 2019-20, the Ministry constructed 10,237 km and in 2021-22, 10,457 km of NHs were constructed.

National Highways construction between 2014-15 and 2022-23 (upto 31 January).


National Highway Construction in km and km per day between 2014-15 and 2022-23 (upto 31 January).

The increase in average construction per day is a welcome change for the Ministry as it was reporting a slower pace of road construction until December last year.


Join our WhatsApp channel - no spam, only sharp analysis