How India's Rs 18,000 Crore International Container Transshipment Terminal On Nicobar Island Will Take Shape

  • As part of the island development project, four projects namely, a port, greenfield international airport, township and a power plant are slated to come up at Great Nicobar Island.

Amit MishraJan 30, 2023, 12:38 PM | Updated 01:31 PM IST
Great Nicobar Island.

Great Nicobar Island.


The Ministry of Ports, Shipping and Waterways has invited expressions of interest (EOI) from interested parties to develop first phase of international container transshipment port (ICTP) project at Great Nicobar Island, in the Bay of Bengal. 

Development of a greenfield port is part of the Island Development program which envisages holistic development of the Great Nicobar Island.


The proposed port will come at Galathea Bay in Great Nicobar Island of the Union Territory of Andaman and Nicobar Islands.

Overall layout of proposed development plan at Great Nicobar Island.

The environmental clearance for all these projects has been accorded.


Transshipment is when a cargo or a container is moved from one vessel to another, while in transit to its final destination.

Location of proposed port.

The Galathea Bay has a natural draft of 20 metres and hence, provides a natural advantage for transshipment.

The bay is strategically located along the international trade route in the Indian Ocean Region, midway between existing transshipment terminals at Singapore, Klang and Colombo.


The transshipment port, with its higher draft and greater efficiency, will provide an alternative option to shipping lines for containers transshipment along Malacca Strait.

The Straits of Malacca is a narrow stretch of water in South-East Asia and is located between the east coast of the Indonesian island of Sumatra and the west coast of the Malay Peninsula.

Strait of Malacca.

The strait is the main and quickest shipping channel between the Indian Ocean and Pacific Ocean, and handles about 35 per cent of the annual global sea trade.

Phase-Wise Expansion


The first phase, upon completion in 2028, will handle 4 million containers per year. The estimated cost for the first phase of the port is Rs 18,000 crore.

Layout of the Phase 1 Port Development.

Global-level infrastructure such as breakwaters, 400 m wide navigational channel, container yard, container berth, container handling equipment, two liquid cargo berths to support bunkering operations and ship repair facilities are some of the key facilities to be developed as part of the first phase of ICTP project.

Landlord Mode

Syama Prasad Mookerjee Port, Kolkata (SMPK) is the nodal agency for undertaking development of proposed port project in landlord mode.

In this model, the publicly governed port authority acts as a regulatory body and as a landlord, while private companies carry out port operations — mainly cargo-handling activities.

Here, the port authority maintains ownership of the port, while the infrastructure is leased to private firms that provide and maintain their own superstructure and install their own equipment to handle cargo. In return, the landlord port gets a share of the revenue from the private entity.


On the other hand, the chosen Concessionaire will design, finance, construct, operate and maintain the container handling facilities envisaged in Phase-I under a long-term concession agreement of 30-50 years.

The Concessionaire shall have the flexibility to develop storage area and handling equipment based on their market assessment subject to the minimum guaranteed traffic. It will be responsible for the provision of port services and shall have the rights to levy, collect and retain charges from port users.

The EOI pertaining to ICTP, Galathea Bay has been released on 28 January 2023 and interested parties can submit their bids by 7 March 2023.