Civil works on Namma Metro’s Vellara Junction-Pottery Town 5.63-km underground stretch is likely to begin in about six months, reports Economic Times.
The Rs 2,628-crore project was awarded to Larsen & Toubro by the Bangalore Metro Rail Corporation Limited (BMRCL).
According to the firm, L&T will have 42 months to complete tunneling at Vellara Junction, MG Road, Cantonment, Pottery Town and Shivajinagar stations.
According to the contract, L&T would deploy four Tunnel Boring Machines, priced at between Rs 50 crore and Rs 100 crore, depending on their type.
BMRCL earlier had a bitter experience completing the underground work of Phase I as contractors used “wrong Tunnel Boring Machines”. This delayed the completion by 2-3 years. It took about five years to tunnel a 10-km section.
“Bengaluru has a complex geology, which is a mix of rocks and boulders. Therefore, a proper study of the tunnelling medium is required before deploying the TBM,” said a scientist with the Department of Geophysics in the report.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.
Latest