The much-delayed Delhi-Gurugram-Dwarka expressway is expected to be completed within one year from now, an official said on Wednesday (12 February).
According to a senior official of the National Highway Authority of India (NHAI), 30 per cent of this expressway has already been completed. The contracts pertaining to the construction of the project have awarded to four construction companies with a strict timeline.
"We have divided into four packages this 16 lanes expressway starting from the Delhi Gurugram expressway at Shiv Murti and going all the way to Kherki Dhaula toll plaza via Dwarka Sector 21, Gurugram border and Basai," the NHAI official said.
The first package starts from Shiv Murti to Dwarka Sector 21 covering 5.3 km, the second package is 4.2 km from Dwarka Sector 21 to the Gurugram border, the third package is from the Gurugram border to Basai flyover having distance of 10.2 km and the fourth package from Basai to Kherkidhaula on National Highway (NH) 8.
An 18.9 km stretch of the expressway falls under Gurugram, while the remaining 9.5 km falls under the territories of Delhi.
Following over 10 years of delay, the foundation stone of the expressway was laid on 8 March, 2019, by Road Transport Minister Nitin Gadkari.
"The project of the Dwarka expressway has been delayed due to non-acquisition of land in Delhi. The total cost of the project is Rs 7,500 crore and provides signal-free travelling experience to commuters who can reach from one point to another in 20 to 25 minutes. It will remove the traffic burden of existing Delhi-Gurugram expressway," the official said.
The initial concept of the 6-lane 18 km long expressway connecting NH 8 at Kherkidhaula with Delhi's suburb of Dwarka surfaced in 2007 and its construction started in 2009 with a completion time of 36 months.
However, the project was delayed due to land acquisition issues in Gurugram faced by the Haryana Shahari Vikash Pradhikaran, and in Delhi faced by the Sheila Dixit and Arvind Kejriwal governments.
(This story has been published from a wire agency feed without modifications to the text. Only the headline has been changed.)
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.
Latest