Modern Coach Factory Creates Record, Rolls Out 554 LHB Coaches In First Four Months Of FY20 

Swarajya StaffAug 08, 2019, 11:05 AM | Updated 11:05 AM IST
View of LHB coaches of Indian Railways (representative image) (Facebook)

View of LHB coaches of Indian Railways (representative image) (Facebook)


As the Indian Railways is planning to replace all the existing coaches of its trains with the Linke Hofmann Busch (LHB) coaches, the Modern Coach Factory (MCF) in Raebareli has manufactured a record number of 554 LHB coaches in the first four months of the FY 2019-20, reports Rail Analysis India.

The unit has raised its production by more than 50 per cent compared to the same period in last year when 368 LHB coaches were rolled out.

In July alone, the factory has produced 142 LHB coaches. The increase can be attributed to the commissioning of robotic manufacturing lines of sidewall, underframe and shell assembly, supply-chain management and the constant monitoring and coordination during production.

Set up to initially manufacture 1,000 LHB coaches per annum, the MCF has now got an additional Rs 480-crore expansion project to enhance the production up to 2000 coaches per annum.

The unit had manufactured 1,425 LHB coaches last year and was set a target of 1,458 for this year. Owing to the fast-paced production, the target is now revised to 2,158 coaches.