Insta
Construction underway in Package 4 of the Bundelkhand Expressway. (UPEIDA)
Almost 69 per cent of the 296 km long Bundelkhand expressway has been completed. According to the latest progress report, 687 out of 818 structures in the project have been built.
The CEO of UP Expressways Industrial Development Authority (UPEIDA), Awanish Awasthi, conducted a virtual meeting of the Bundelkhand Expressway and instructed officials to expedite the remaining works of the expressway.
During the meeting, officials informed that out of 296 km of the expressway, around 213 km of this four-lane expressway is complete, reports Hindustan Times.
The foundation of the expressway was laid by Prime Minister Narendra Modi on 29 February last year in the Chitrakoot district of Uttar Pradesh.
Apco Infra is working on Packages 1 and 2, Ashoka Buildcon on Package 3, Gawar Constructions on Packages 4 and 5 and Dilip Buildcon on Package 6.
Originating near Bharatkoop in the Chitrakoot district, the e-way passes through Banda, Mahoba, Hamirpur, Jalaun, Auraiya and Etawah.
It joins the Lucknow-Agra Expressway near Kudrail village in the Etawah district, linking the drought-prone Bundelkhand in southern UP and northern Madhya Pradesh to the National Capital Region through the Lucknow-Agra and Yamuna (Agra-Noida) expressways.
The expressway is critical to the success of the Defence Corridor coming up in Uttar Pradesh. Two nodes of the Defence Corridor, Jhansi, and Chitrakoot, are in Bundelkhand. Connectivity between these and the other corridor nodes — Agra, Lucknow, Kanpur and Aligarh — will improve with its construction.
The Yogi Adityanath government has allocated Rs 1,492 crore for the 296-km long Bundelkhand Expressway in the 2021 budget.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.
Latest