Central Infrastructure Projects Face Rs 5.6 Lakh Crore Overrun And Delays
V Bhagya Subhashini
May 30, 2024, 04:29 PM | Updated 04:32 PM IST
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
The ratio of cost overruns in central government projects surged to a 12-month high of 20.09 per cent in April, up from 18.65 per cent in the previous month, according to government data released on Tuesday (28 May).
The anticipated cost of 1,838 projects, each valued at Rs 150 crore or more, totalled Rs 33.2 lakh crore. This figure was Rs 5.6 lakh crore higher than the original estimated cost. Additionally, the ratio of delayed projects increased compared to the previous months.
Out of these projects, 43 per cent (792 projects) were delayed with respect to their original completion date, and 514 projects were delayed in terms of their original cost as well. Government data indicated that 61 projects were completed in April, while 29 new projects were initiated.
The cost of completed projects in April was Rs 46,649.7 crore, whereas the newly added projects had an estimated cost of Rs 1.3 lakh crore.
The government’s focus on infrastructure development has been highlighted by international agencies as a key driver of growth and is expected to continue in the coming year.
Economic Times report suggested that the economy likely grew by 7.8 per cent in FY24 and is projected to grow by 6.8 per cent in the current fiscal year.
Despite the rise in cost overruns in April, the average time for project completion decreased to 35.4 months, compared to 36.04 months in March. However, 48 per cent of the projects experienced delays of over two years.
The government report noted that 54 of the 1,838 projects, which had time overruns exceeding 50 months and cost overruns over 50 per cent, contributed 43.39 per cent of the total cost overrun and 21.34 per cent of the total time overrun.
Among the major sectors, the railways faced the highest cost overruns at 126.5 per cent in April, with over half of its projects registered with the government experiencing cost overruns. The road transport and highways sector, which accounts for nearly 60 per cent of the projects, had a cost overrun ratio of 23.7 per cent.
Additionally, one-third of railway projects and over 10 per cent of road projects faced time overruns, according to government data.
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Support Swarajya's 50 Ground Reports Project & Sponsor A Story
Every general election Swarajya does a 50 ground reports project.
Aimed only at serious readers and those who appreciate the nuances of political undercurrents, the project provides a sense of India's electoral landscape. As you know, these reports are produced after considerable investment of travel, time and effort on the ground.
This time too we've kicked off the project in style and have covered over 30 constituencies already. If you're someone who appreciates such work and have enjoyed our coverage please consider sponsoring a ground report for just Rs 2999 to Rs 19,999 - it goes a long way in helping us produce more quality reportage.
You can also back this project by becoming a subscriber for as little as Rs 999 - so do click on this links and choose a plan that suits you and back us.
Click below to contribute.