Green Energy Corridor Phase-2 Approved With Rs 12,000 Crore To Add Transmission Capacity To Evacuate 20 GW Renewable Power

by India Infrahub - Jan 7, 2022 01:45 PM +05:30 IST
Green Energy Corridor Phase-2 Approved With Rs 12,000 Crore To Add Transmission Capacity To Evacuate 20 GW Renewable PowerPower transmission lines. (Flickr)

The Cabinet Committee on Economic Affairs (CCEA) on Thursday (6 January) approved the scheme on Green Energy Corridor (GEC) Phase-II for Intra-State Transmission System (InSTS) for the addition of approximately 10,750 circuit kilometres (ckm) of transmission lines and 27,500 MegaVolt-Amperes (MVA) transformation capacity of substations.

The scheme will facilitate grid integration and power evacuation of approximately 20 GW of Renewable Energy (RE) power projects in seven states: Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh.

The scheme is targeted to be set up with a total estimated cost of Rs 12,031 crore and Central Financial Assistance (CFA) of 33 per cent of the project cost, i.e. Rs 3,970 crore.

The transmission systems will be created over five years from Financial Year 2021-22 to 2025-26.

“The Central Financial Assistance (CFA) will help in offsetting the Intra-State transmission charges and thus keep the power costs down. Thus, the Government support will ultimately benefit the end users — the citizens of India,” the official statement said.

Besides helping achieve the target of 450 GW installed RE capacity by 2030, the scheme will also contribute to long term energy security and promote ecologically sustainable growth by reducing carbon footprint.

This scheme is in addition to GEC phase-I, which is already under implementation in the states of Andhra Pradesh, Gujarat, Himachal Pradesh, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan and Tamil Nadu for grid integration and power evacuation of 24 GW of RE power and is expected to be completed by 2022.

The scheme is for the addition of 9,700 ckm of transmission lines and 22,600 MVA capacity of substations, having an estimated cost of Rs 10,141 crore with Central Financial Assistance (CFA) of Rs 4,056 crore.

Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.