Just 33 Per Cent Of Land Acquisition Completed In Maharashtra For Mumbai - Ahmedabad Bullet Train Project: Report

by India Infrahub - Nov 6, 2021 11:56 AM +05:30 IST
Just 33 Per Cent Of Land Acquisition Completed In Maharashtra For Mumbai - Ahmedabad Bullet Train Project: ReportA bullet train (Photo via NHRSCL Website)

The National High-Speed Rail Corporation Limited (NHSRCL), the executing agency of high-speed rail corridor in India, has acquired 33 per cent of land in Maharashtra required for the construction of the Mumbai-Ahmedabad bullet train corridor.

With a total of twelve stations in the States of Maharashtra, Gujarat and Union Territory of Dadra and Nagar Haveli, the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor will have a length of 508.17 Km.

In Gujarat, 1,084 hectares of the required 1,396 hectares have been acquired. In Dadra and Nagar Haveli, 93 hectares of the required 95 hectares has been acquired for the corridor.

However, in Maharashtra, just 143 hectares of land has been acquired out of 432 hectares of land required for the project, reports Hindustan Times.

The slow progress of land acquisition in Maharashtra was a cause of concern, as this delay may cause the bullet train project to miss its deadline.

Recently, Minister of State for Railways, Raosaheb Patil Danve, chaired a review meeting on the Western Dedicated Freight Corridor (WDFC) and Mumbai – Ahmedabad High-Speed Rail (MAHSR) project at the headquarters of Western Railway in Mumbai.

Emphasising the importance of these two projects, the minister directed authorities, including the state government officials, to expedite the work for completion of projects within the stipulated target period to avoid cost and time overruns.

On the other hand, Indian Railways has expedited the construction of the country’s first high-speed rail corridor with a set target of building 50 piers every month.

It must be noted that there is no standard design for all pillars of the high-speed corridor. Each pillar requires a unique design depending on soil conditions. Presently Soil testing of the site, where pillars are constructed and their designing is done.

Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.