Infrastructure
Arun Kumar Das
Jul 19, 2022, 10:39 AM | Updated 10:39 AM IST
Save & read from anywhere!
Bookmark stories for easy access on any device or the Swarajya app.
Focusing on acquiring new technology in train service, Indian Railways has invited leading rolling stock players to manufacture 100 upgraded Vande Bharat trainsets with articulated bogie, aluminium body and sleeper facilities to run at a maximum speed of 200 kmph.
Articulated technology is capable of negotiating curves on the tracks without losing the speed and so reducing the running time to some extent.
The Rs 30,000 crore tender was floated for manufacturing of state-of-the-art Vande Bharat trains to run at higher speed than the existing 160 kmph train as the Railways has plans to upgrade its tracks and signalling system for 200 kmph speed.
While the first pre-bid would be held on 23 August, the last date of bid submission is 25 November.
Currently, Delhi-Mumbai and Delhi-Howrah routes are being upgraded for running trains at 160 kmph speed. "Since these aluminium bodied Vande Bharat trains will have codal life of 35 years, the railways is likely to strengthen its tracks and upgrade signalling system for 200 kmph run in future," said a senior Railway Ministry official.
Besides these two corridors, other trunk routes are also slated to be upgraded in due course.
The latest Vande Bharat tender envisages 100 trainsets equipped with articulated bogie and concentrated power car system, a first in Indian Railways.
Also known as push-pull system as the trainset would be hauled by two locomotives at the rear and front of the train, a departure from the distributed power system.
The Railways aims to deliver 75 Vande Bharat trains by 23 August next year and one such train is expected to be rolled out before 15 August this year.
Earlier, two Vande Bharat trains were expected to roll out from the Integral Coach Factory at Chennai. However, due to the Ukraine war and supply chain problem, the manufacturing process got disrupted.
Now, one Vande Bharat prototype train is being readied for roll out in August and the second one is expected in September. After rolling out, the prototype would be on trial run for 45 days before being commissioned for the service.
While Vande Bharat trains with seating facilities would replace Shatabdi and intercity services, Rajdhani trains would be replaced by Vande Bharat trainsets with sleeper facilities.
Currently, two Vande Bharat trains are operational to Varanasi and Katra from the capital. Finance Minister Nirmala Sitharaman had announced in her budget 2022-23 for bringing about 400 more Vande Bharat trains.
Arun Kumar Das is a senior journalist covering railways. He can be contacted at akdas2005@gmail.com.