Pune Metro Now Rs 185 Crore Dearer, Route Diverted To Steer Away From Aga Khan Palace
Pune Metro Now Rs 185 Crore Dearer, Route Diverted To Steer Away From Aga Khan PalacePune metro construction. (pic via Twitter)

The Maharashtra Metro Rail Corporation (MMRC) will be diverting the route of the Pune Metro due to the rejection of its current route by National Monuments Authority which refused to permit its current route, Metro Rail News has reported. Its current route was in the vicinity of Aga Khan Palace which is a protected monument.

The diversion will now increase the cost of the Pune Metro project by Rs 185 crores. In a communication to Pune Metro, the MMRC suggested three options out of which it recommended the second option. This involves diversion of the route from Gunjan Chowk and an increase of the length of viaduct by 0.92 km.

As per the Ancient Monuments and Archaeological Sites and Remains Act of 1958, no construction is allowed within a 100-metre radius of a protected monument. The Aga Khan Palace was declared as a nationally protected monument in the year 2003.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Advertisement