Mumbai Metro: Section Of Bandra-Colaba-SEEPZ Line And Aarey Car Shed To Be Operational By December 2023

by V Bhagya Subhashini - Nov 29, 2022 12:03 PM +05:30 IST
Mumbai Metro: Section Of Bandra-Colaba-SEEPZ Line And Aarey Car Shed To Be Operational By December 2023Mumbai Metro Line-3.

Mumbai Metro Rail Corporation Limited (MMRCL) has said that work on the first and only underground metro network in Mumbai, Line-3, popularly known as the Bandra-Colaba-SEEPZ Line, has been 76.6 per cent complete.

According to S K Gupta, Director (Projects), MMRCL, the first section of the Mumbai Metro Line-3 between Aarey Milk Colony and Bandra-Kurla Complex and the Aarey Car Shed will be operational by December 2023.

Metro Line-3 is a 33.5 km-long underground corridor running along Colaba-Bandra-SEEPZ. The length of the corridor is marked with 27 key stations, out of which 26 will be underground.

“The first phase of the project between Aarey Colony and BKC would be operational by December 2023. The Aarey car shed would also be operational by then. The stations in the stretch including Aarey Colony station would be ready by December next year,” said Gupta.

"The second phase between BKC and Colaba would take another six months and would be completed by mid-2024," he added, reports Deccan Herald. 

Mumbai Metro Line 3 Route Map ( MMRCL)
Mumbai Metro Line 3 Route Map ( MMRCL)

Metro Line-3 would connect Mumbai’s key financial hubs, such as Nariman Point, Bandra-Kurla-Complex, Fort, Worli, Lower Parel, Goregaon, etc.

The metro will provide, for the first time, connectivity to the airport, Nariman Point, Cuffe Parade, Kalbadevi, Worli, BKC, Airport, SEEPZ and MIDC.

Besides, two crucial heritage stations in Mumbai — CSTM and Churchgate — will also be connected through the alignment.

The metro trains will run on a 25 KV AC traction supply and have a maximum passenger carrying capacity of 2,350.

The trial run of the prototype rake for Metro 3 (Colaba-Bandra-SEEPZ section) began on 30 August on a 3 km stretch between Sariput Nagar and Marol Naka Metro Station. 

About 17 tunnel boring machines (TBMs) worked simultaneously for the first time on an underground metro project when the tunnelling began in November 2017.

The project is estimated to have a total cost of about Rs 38,000 crore. Of the total project cost, 50 per cent is being funded by the Japan International Cooperation Agency as a soft loan and 20 per cent by the Union government.

Originally, the line's construction was scheduled to be completed in 2021. However, work delays caused the deadline to be missed, and the project cost increased from Rs 23,136 crore to Rs 38,000 crore.

Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.