Work On First River Bridge On Bullet Train Corridor Nearing Completion

by Amit Mishra - Jan 25, 2023 11:22 AM +05:30 IST
Work On First River Bridge On Bullet Train Corridor Nearing CompletionPier Works on Par River
Snapshot
  • The bridge being constructed over Par River in Valsad, Gujarat is 320 metres long and consists of eight full-span girders, each 40 metres long.

In a significant achievement, the first river bridge on the Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor is getting ready and is just four pillars away from completion.

The bridge being constructed over Par River in Valsad in Gujarat is 320 metres long and consists of eight full-span girders, each 40 metres long. The height of pier on which these girders will rest, ranges from 14.9 to 20.9 metres.

Among the most complex of the substructures being constructed on the high speed corridor are the bridge structures over rivers.

“Laying piers on a river is complex. It involves complex geotechnical investigation. First, the well foundation has to be laid. Then piers will be put, over which the girders will be launched. Finally, the track will come on the girder,” said a senior official overseeing the construction of the bridge on the Tapi River.

A total of 20 bridges will be constructed under this project as the bullet train will cross over rivers like Narmada, Sabarmati, Mahi, Par, Kaveri, Purna Ambika, Daroatha, Daman Ganga, Tapi, Kim, Vishwamitri, Mohar, Vatrak and Meshwa.

The longest will be a 1.2-km-long bridge over the Narmada river in Bharuch city of Gujarat followed by Tapi and Mahi which will be around 720 meters.

India’s First Bullet Train Project

Presently, the Mumbai-Ahmedabad High-Speed Rail is the only sanctioned high-speed rail project in the country.

The High-Speed Rail operating at 320 kmph will traverse along west India’s landscape, covering 508.17 km distance between Mumbai and Ahmedabad in just about two hours. This will save time compared to current travel time between the two terminal stations by about nine hours (by bus) or six hours (by conventional railways).

It will cover 155.76 km in Maharashtra, 4.3 km in the Union Territory of Dadra & Nagar Haveli and 348.04 km in Gujarat, with 12 stations en route.

The government is yet to determine a final deadline for the entire 508-km project, but the completion time for a 50-km stretch between Surat and Bilimora in Gujarat has been set for August 2026.

Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.