Chennai Metro Phase II: Special Tunnel Boring Machines To Be Used In Madhavaram-SIPCOT Line

Chennai Metro Phase II: Special Tunnel Boring Machines To Be Used In Madhavaram-SIPCOT Line

by V Bhagya Subhashini - Oct 20, 2022 12:24 PM +05:30 IST
Chennai Metro Phase II: Special Tunnel Boring Machines To Be Used In Madhavaram-SIPCOT Line Tunnel boring machine Terratec.
Snapshot
  • The estimated cost of the Phase II project is Rs 63,246 crore. Construction is expected to be completed by the end of 2026. 

Chennai Metro Rail Limited (CMRL) intends to deploy two specialised tunnel boring machines (TBM) to handle some portions of the underground work in the stretch between Royapettah and Taramani on Corridor-3.

It is due to the rocky terrain underground.

Tunnelling work began last week at Madhavaram as part of the Phase II project on Corridor-3 from Madhavaram to SIPCOT. 

The expansion of Metro Phase II is planned with a network length of 118.9 km with 128 stations. It consists of three corridors:

  • Corridor-3 - From Madhavaram to SIPCOT (45.8 km)

  • Corridor-4 - From Lighthouse to Poonamalle Bypass (26.1 km)

  • Corridor-5 - From Madhavaram to Sholinganallur (47 km).

The estimated cost of the Phase II project is Rs 63,246 crore. Construction is expected to be completed by the end of 2026. 

Map of Chennai Metro Rail Project Phase - II Source: CMRL
Map of Chennai Metro Rail Project Phase - II Source: CMRL

CMRL will construct underground stations and tunnels in corridor-3 from Madhavaram to Taramani, and after that, the metro will rise as an elevated segment all the way to SIPCOT. 

The Phase II project will require 23 TBMs. Only eight will be working on tunnels between Kellys and Taramani, and of those, two will be used to drill through rock specifically. 

CMRL officials said TBMs can normally bore nearly 10 metres per day, but in the presence of hard rock, even these special TBMs can only drill three–four metres per day.

"The soil conditions are definitely manageable from Madhavaram to Kellys. The first 5-7 metres will be sandy, and then we'll run into marine clay," an official said, reports The Hindu

In Phase II, the stations are built at a depth of 18–20 metres, and in a few locations, like Mylapore and Taramani, it goes as deep as 25 metres.

"At Taramani, there will be a rock at a depth of 13–14 metres and hence it could pose a major challenge," the report added.

Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.