Railways To Develop New Rail Track At Grade Between Bangalore And Secunderabad For 200 Kmph Train

by Arun Kumar Das - Aug 13, 2022 11:15 AM +05:30 IST
Railways To Develop New Rail Track At Grade Between Bangalore And Secunderabad For 200 Kmph Train  Indian Railways to develop semi-high speed rail track compatible for running train at 200 kmph.

Indian Railways is actively considering to develop a semi-high speed track compatible for running train at 200 kmph speed on the surface level close to the existing track between Bangalore and Secunderabad as a greenfield project at an estimated cost of Rs 30,000 crore.

While the total length of existing track between the two cities is 622 km, the Railways is planning to reduce it to 503 km from Umdanagar near Secunderabad to Yelahanka in Bangalore as part of the Gati Shakti initiative.

Estimated to cost about Rs 60 crore per km including the low side walls on both sides, the proposed route is an attempt to economise on cost by avoiding multiple detours.

Fencing or sidewalls at both sides of the track is a must for semi-high speed trains. It has been proposed to build 1.5 metres height sidewalls along the new track to provide an exclusive right of way to the semi-high speed rail operations.

The elevated route with viaducts like RRTS corridor between Delhi and Meerut or Mumbai-Ahmedabad bullet train route is slated to be around Rs 300 crore per km.

Due to road over bridges (ROB) in city areas, an elevated track along the existing tracks would require multiple detours - leading to requirement of number of vertical - horizontal curves.

Currently, the Railways is upgrading two routes between Delhi-Mumbai and Delhi-Howrah for running trains at 160 kmph speed.

However, discarding the option of upgrading the existing track to 200 kmph level, the Railways would now explore the possibility of developing semi-high speed track at grade level as a demonstrative project to begin with.

As per the plan, a new line would be constructed with a separate train control system and signalling near the existing track for which a detailed project report would be commissioned shortly. The indigenously developed signaling system Kavach meant for 160 kmph and above speed.

The ambitious Gati Shakti project connecting two IT cities is still in the drawing board stage, the preparatory work has begun for the detailed project report.

The Railways has recently floated tenders for manufacturing of 200 Vande Bharat trains with maximum speed of 200 kmph.

As part of the rolling stock modernisation plan, the Railways is gearing up for modern systems such as articulated bogie or tilting coaches, the state-of-the-art technology along with an upgraded version of train communication system.

Besides, there would be 302 Vande Bharat trains with 160 kmph speed. So our rolling stocks are becoming compatible for semi-high speed operation, said a senior Railway Ministry official.

Also Read: Nine New Railway Line Projects Approved In Last Three Years, Says Railway Minister

Arun Kumar Das is a senior journalist covering railways. He can be contacted at akdas2005@gmail.com.


Get Swarajya in your inbox everyday. Subscribe here.

An Appeal...

Dear Reader,

As you are no doubt aware, Swarajya is a media product that is directly dependent on support from its readers in the form of subscriptions. We do not have the muscle and backing of a large media conglomerate nor are we playing for the large advertisement sweep-stake.

Our business model is you and your subscription. And in challenging times like these, we need your support now more than ever.

We deliver over 10 - 15 high quality articles with expert insights and views. From 7AM in the morning to 10PM late night we operate to ensure you, the reader, get to see what is just right.

Becoming a Patron or a subscriber for as little as Rs 1200/year is the best way you can support our efforts.

Become A Patron
Become A Subscriber
Comments ↓
Get Swarajya in your inbox everyday. Subscribe here.
Advertisement

Latest Articles

    Artboard 4Created with Sketch.